We found 3 possible routes

Here is a simple comparison. You can explore each option before choosing one for further study.

  • Shortest route

    Route A

    9.4 km

    • Shortest distance
    • Simple connection to the Wash Plant
    • Crosses future Mining Area B
    • More operational disruption risk

    Good distance, but may conflict with future mining.

  • Recommended

    Route B

    10.8 km

    • Avoids known future mining area
    • Gentler terrain
    • Fewer water crossings
    • Good access for future maintenance
    • Slightly longer than Route A

    Best balance of distance, terrain and future mine activity.

  • Lowest new land disturbance

    Route C

    12.1 km

    • Uses more already-disturbed land
    • Avoids rehabilitation area
    • Longest route
    • More infrastructure required

    Lower new land impact, but likely more expensive to build.

Where would each route go?

Site boundaryCurrent truck route (21 km)Future Mining Area BWater areaRehabilitation areaCommunitySteep groundMining Area AWash Plant
  • Route A · 9.4 km
  • Route B · 10.8 km
  • Route C · 12.1 km

Compare the options

  • DistanceRoute A: 9.4 kmRoute B: 10.8 kmRoute C: 12.1 km
  • Future mine conflictRoute A: HighRoute B: LowRoute C: Low
  • Terrain difficultyRoute A: MediumRoute B: LowRoute C: Medium
  • Water crossingsRoute A: 3Route B: 1Route C: 2
  • New land disturbanceRoute A: MediumRoute B: MediumRoute C: Low
  • Maintenance accessRoute A: GoodRoute B: Very goodRoute C: Fair

Best overall option: Route B

TerraOps recommendation

Route B is the strongest option for further engineering review.

Why?

  • It avoids the known future mining area.
  • It has gentler terrain.
  • It has fewer water crossings.
  • It gives good access for maintenance.
  • It makes a reasonable connection to the Wash Plant.

Recommended next step

Send Route B for engineering feasibility review.

MineFlow is an early planning and option-comparison tool. Detailed engineering, surveying and technical studies are still required before construction.