TerraOpsDemo Mining Group

TerraOps Portfolio Update

Demo Mining Group

26 August – 1 September 2026

Prepared 6 Sep 2026 by James Dlamini

Portfolio overview

  • 4

    sites

  • 6

    important changes

  • 11

    open tasks

  • 3

    projects need management review

Sites needing attention

  • Ndlovu Mine

    One inspection is overdue and a road project shows a large difference between reported and visible progress.

    Status: Urgent

  • Mhlabeni Coal Mine

    New ground disturbance and rehabilitation issues require review.

    Status: Needs attention

Sites operating normally

  • Madiba North Mine

    1 change to review

    2 open tasks

    No urgent issues

    Status: Looks good

  • Masakhane Mine

    No urgent changes

    3 tasks in progress

    Status: Looks good

Most important items this week

  1. 1Ndlovu Mine: one inspection is overdue and has not been completed.
  2. 2Ndlovu Mine: a road project shows a large difference between reported and visible progress.
  3. 3Mhlabeni Coal Mine: about 0.8 hectares of new work may sit outside the planned area.
  4. 4Mhlabeni Coal Mine: Rehabilitation Area R12 remains under review.
  5. 5Mhlabeni Coal Mine: Route B is ready to be sent for engineering feasibility review.

Management actions recommended

  1. 1Ask the Ndlovu site manager to complete the overdue inspection this week.
  2. 2Request a field verification of the West Access Road upgrade at Ndlovu Mine.
  3. 3Confirm the Mhlabeni boundary question with the operations team.
  4. 4Close out the remaining Rehabilitation Area R12 concern.
  5. 5Approve the Route B engineering feasibility review.

Demo portfolio: all sites, findings and figures in this report are fictional demo examples.