Weekly Update
Mhlabeni Coal Mine
2–8 September 2026
Prepared 8 Sep 2026 by James Dlamini
Quick summary
3
important changes
5
open tasks
2
inspections in progress
2
projects need review
What changed?
New land disturbance
4.7 hectares changed near Mining Area A.
About 0.8 hectares may be outside the planned working area.
Status: Inspection completed
Rehabilitation Area R12
Recovery remains slower than expected.
Status: Corrective action in progress
North Water Area
Visible surface water increased by approximately 12%.
Status: Inspection in progress
Work completed
| Work | Area | Person | Result |
|---|---|---|---|
| Review Rehabilitation Area R12 | Rehabilitation Area R12 | Lerato Nkosi | There is a problem |
| Inspect Mining Area A eastern edge | Mining Area A | Thabo Mokoena | There is a problem |
Work still open
| Work | Area | Due | Status |
|---|---|---|---|
| Inspect new land disturbance | Mining Area A | Today | Needs doing |
| Check North Water Area | North Water Area | Today | In progress |
Projects
Rehabilitation Area R12
Reported: 100%
TerraOps can observe: About 92%
Field check: Completed
Status: Needs review
Mhlabeni Plant Expansion Earthworks
Reported: 72%
TerraOps can observe: About 68%
Field check: Not needed yet
Status: Looks on track
East Access Road
Reported: 85%
TerraOps can observe: About 61%
Field check: Not yet available
Status: Needs attention
Planning
Mining Area A → Wash Plant Conveyor
Recommended option: Route B
Status: Ready for engineering review
Recommended next actions
- 1Review remaining Rehabilitation Area R12 concern.
- 2Complete North Water Area inspection.
- 3Send Route B for engineering feasibility review.
This report is a demo example built from illustrative TerraOps information.