Earthworks · Mhlabeni Coal Mine

Mhlabeni Plant Expansion Earthworks

Looks on track

Reported

72%

By Engineering team

Observable

About 68%

From satellite pictures

Field check

Not needed yet

No inspection yet

What does this mean?

The visible earthworks appear reasonably close to the reported progress. No major difference has been identified.

See it for yourself

Two satellite pictures of Wash Plant, with the planned work drawn on top.

Satellite picture of Wash Plant — Now

Now · 4 Sep 2026

  • Planned area
  • Appears complete

Illustrative example. The shapes show roughly where the work was planned and what can be seen from above.

What was reported?

The engineering team reported that earthworks are 72% complete.

What can TerraOps observe?

Graded platforms and access roads cover about 68% of the planned area in the latest image.

What did the field team find?

No field inspection has been needed for this project so far.

What should happen next?

Continue monitoring. Check again after the next satellite observation.

How sure are we?

Medium confidence

Earthworks are visible from above, but the finishing work inside the platforms cannot be seen.

How the evidence built up

  1. 3 MarProject started
  2. 14 JulEngineering team reported 48%
  3. 20 AugSatellite observation
  4. 1 SepEngineering team reported 72%
  5. 4 SepTerraOps observation
  6. TodayLooks on track

What would you like to do?

Demo — illustrative example. The percentages shown here are examples for this demo mine, not measurements from a real site.