What was reported?
The contractor reported that the road is 85% complete.
Road · Mhlabeni Coal Mine
Reported
85%
By Contractor
Observable
About 61%
From satellite pictures
Field check
Not yet available
No inspection yet
A large section of the planned road does not yet appear complete in the latest available imagery.
Two satellite pictures of Eastern boundary, with the planned work drawn on top.

Now · 4 Sep 2026
Illustrative example. The shapes show roughly where the work was planned and what can be seen from above.
The contractor reported that the road is 85% complete.
About 61% of the planned road corridor shows a completed road formation. The remaining section still looks like cleared ground.
No field evidence has been collected yet.
Request a field inspection before accepting the reported progress.
High confidence
A new road is easy to see from above, and part of it is not there yet.
Demo — illustrative example. The percentages shown here are examples for this demo mine, not measurements from a real site.